EstimateActivityDurationsistheprocessofe

Freeti2019-12-17  7

问题 EstimateActivityDurationsistheprocessofestimatingthenumberofworkperiodstocompleteindivitieswithestimatedresources.Thetoolsandtechnquesisnotincluding( ).

选项 A:expertjudgmentB:analogousestimatingC:requirementstraceabilitymatrixD:three-pointestimating

答案C

解析