11.编制内外砖墙分部分项工程量清单(阳台隔墙并入内墙计算)(35分)

shuhaiku2020-05-20  33

问题 11.编制内外砖墙分部分项工程量清单(阳台隔墙并入内墙计算)(35分)

选项

答案

解析[img]/upload/tiku/557/2271611_1.png[/img]计算过程1.370墙4分①轴+⑨轴=((2.1+2.4+0.9+0.6+0.25{轴外}×2)×(5.8-0.4{梁高}×2)-(0.9×1.9{C6}))×2=61.58m2②轴+⑧轴=(5.1+0.37{轴外})×(5.8-0.4{梁高}×2)×2=54.7m2③轴+⑦轴=((0.9+0.6+0.37{轴外})×(3-0.4{梁高}))×2=9.72m2④轴+⑥轴=((0.9+0.6+0.37{轴外})×(3-0.4{梁高}))+(0.6+0.37{轴外})×3.6{建施三E轴}×2=16.71m2A轴=((6-0.12{轴内})×(2.8-0.4{梁高})-(1.2×2.1{C2}+2.4×2.6{TM1}))×2=13.06m2A轴=((6-0.12{轴内})×(2.8-0.4{梁高})-(1.2×1.9{C4}+2.4×2.4{Tm3}))×2=12.14m2B轴=((1.2-0.37{轴内})×(3.0-0.4{梁高})-(0.83×2.1{C3}))×2=0.83m2B轴=((1.2-0.37{轴内})×(2.8-0.4{梁高})-(0.83×1.9{C5}))×2=0.83m2D轴=((2.1-0.25{轴内}×2)×(3.0-0.4{梁高})-(1.2×2.6{M1}))×2=2.08m2E轴=((2.7-0.12{轴内})×(3.0-0.4{梁高})-(1.5×2.1{C1}))×2=7.12m2E轴=((2.7-0.12{轴内})×3.6-(1.5×3.6{TM4}))×2=7.78m2F轴=((2.4-0.12{轴内}×2)×(3.0-0.4{梁高})-(1.2×2.1{C2}))×2=6.19m2F轴=((2.4+2.1-0.37{轴内})×(0.5+1.9){墙高}-(1.2×1.9{C4})×2)×2=10.7m2工程量:(61.58+54.7+9.72+16.71+13.06+12.14+0.83+0.83+2.08+7.12+7.78+6.19+10.7)×0.365=74.26m3构造柱=0.37×0.37×5{墙体中的柱高}×9{角柱}+0.37×0.37×2.6×2{一层3轴处}+0.37×0.3×5×2{A轴墙中柱}+0.37×0.24×(2.6+3.6){5轴处}=8.53m3370墙工程量=74.26-8.53=65.72m32.240墙4分③轴+⑦轴=(2.1+2.4-0.25×2{Z1})×(3-0.4{梁高})-(0.8×2.4{m3}+1.8×2.1{Tm2})×2=9.40m2⑤轴=((5.1+2.1+2.4+0.9-0.12{轴内}+2.2{阳台隔墙}+(0.6+1.15){阳台隔墙}-0.37{37墙重合}-0.37×2{构造柱宽})×(3.0-0.4{梁高}))=34.37m2C轴=(2.4-0.24+1.1-0.25{Z1})×(3.0-0.4{梁高})×2=15.65m2B轴=(1.2-0.24+1.1-0.25{Z1})×(3.0-0.4{梁高})×2=9.41m2③轴+⑦轴=(2.1+2.4+0.9+0.6-0.25×2{Z1})×(2.8-0.4{梁高})-(0.8×2.4{m3})×2=22.56m2⑤轴=((5.1+2.1+2.4+0.9-0.12{轴内}+2.2{阳台隔墙}+(0.6+1.15){阳台隔墙}-0.37{37墙重合}-0.37×2{构造柱宽})×(2.8-0.4{梁高}))=31.73m2C轴=(2.4+2.1+2.7-0.24×2-0.25{Z1})×(2.8-0.4{梁高})-(0.8×2.4{m3}+0.9×2.4{m2})×2=22.90m2B轴=(6-0.24-0.25{Z1})×(2.8-0.4{梁高})-(0.8×2.4{m3}+0.9×2.4{m2})×2=17.14m2240墙工程量:(9.4+34.37+15.65+9.41+22.56+31.73+22.90+17.14)×0.24=39.15m33.120墙1分(2.4-0.24)×(2.8-0.4{梁高})×0.115×2=1.19m3
转载请注明原文地址:https://ti.zuoweng.com/ti/G62pKKKQ