计算过程: 1、砖墙工程量=[(8.4-0.24×4)×(6+0.06-0.3×2)+(3.6-0.24)×(6-2.96-0.3)-(3×2.7+1.8

恬恬2020-05-20  27

问题

选项

答案

解析[img]/upload/tiku/557/2271622_1.png[/img]计算过程:1、砖墙工程量=[(8.4-0.24×4)×(6+0.06-0.3×2)+(3.6-0.24)×(6-2.96-0.3)-(3×2.7+1.8×1.8)×2-2.4×2.7]×0.24=4.96m32、脚手架工程量=(8.4-0.24)×(6+0.06-0.3×2)+(3.6-0.24)×(6-2.96-0.3)=53.76m23、单价换算:3-1-14省单价=44×15.38+1345.27+16.49=2038.48元/10m3合同单价=55×15.38+1345.27+16.49=2207.66元/10m310-1-21省单价=44×0.39+5.24+8.29=30.69元/10m2合同单价=55×0.39+5.24+8.29=34.98元/10m2